46 CFR 2.90-1
§ 2.90-1 General requirements.
United States · 46 CFR — Shipping · Status: effective
Cite this
- Citation
- 46 CFR 2.90-1, § 2.90-1 General requirements, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/223128
- Permanent ID
ys:prov:223128@1- SHA-256
528340b9a5d1daf61f93b9c485182d9b70821eecaa94e4c6d35ab45cc44d7762
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) Drawings, blueprints or plans showing the details of construction of vessels subject to inspection or installations thereon are required to be submitted for approval in accordance with applicable regulations in this chapter, information as to which may be obtained at any local Marine Inspection Office.
(b) The requirements for passenger vessel construction are in parts 43-46, 70-78, of this chapter.
(c) The requirements for tank vessel construction are in parts 30-39, 43-45, of this chapter.
(d) The requirements for cargo and miscellaneous vessel construction are in parts 43-45, 90-97, of this chapter.
(e) The requirements for marine engineering installations or equipment are in parts 50-69 of this chapter.
(f) The requirements for electrical engineering installations or equipment are in parts 110-113 of this chapter.
(g) The requirements for items to be manufactured under specific approval by the Commandant are in parts 160-164 of this chapter.
(h) The requirements for vessels carrying certain bulk dangerous cargoes are in parts 148, 151, 153, and 154 of this chapter.
(i) The requirements for subdivision and stability plans and calculations are in part 170 of this chapter.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.