46 CFR 34.20-5
§ 34.20-5 Quantity of foam required—T/ALL.
United States · 46 CFR — Shipping · Status: effective
Cite this
- Citation
- 46 CFR 34.20-5, § 34.20-5 Quantity of foam required—T/ALL, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/224377
- Permanent ID
ys:prov:224377@1- SHA-256
47db444622f5cf5f5bd722a5a8982064c9632c45267e0cd843442c719469de2b
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) Area protected. Systems of this type are designed to give primary protection to the spaces over the cargo tanks.
(b) Rate of application. The water rate of the foam production equipment shall be determined as follows:
(1) For usual petroleum products the rate of supply of foam solution shall be not less than the greatest of the following:
(i) 0.6 liters/min per square meter of cargo tanks deck area, where cargo tanks deck area means the maximum breadth of the ship multiplied by the total longitudinal extent of the cargo tank spaces;
(ii) 6 liters/min per square meter of the horizontal sectional area of the single tank having the largest such area; or
(iii) 3 liters/min per square meter of the area protected by the largest monitor, such area being entirely forward of the monitor, but not less than 1,250 liters/min.
(2) For polar solvent products (e.g. alcohols, ketones, etc.) the water rate shall be determined for each vessel. The rate will depend upon the vessel design, products to be carried and foam system to be used.
(c) Supply of foam-producing material. Each deck foam system must have a supply of foam-producing material sufficient to operate the system at its designed rate of foam production for the following periods:
(1) For installations contracted for on or after January 1, 1970, 15 minutes without recharging, except as required in paragraph (c)(2) of this section.
(2) For installations on ships that have a keel laying date on or after January 1, 1975, 20 minutes without recharging.
(d) Separate supply of foam-producing material. Where the same foam-producing material may be used for this system as well as a fixed foam system, separate supplies need not be provided for each space protected. The total available supply shall be at least sufficient for the space requiring the greatest amount.
(e) Water supply. Suitable pumps shall be provided capable of producing the required water rate. The fire pumps required by subpart 34.10 may be used for this purpose; however, the operation of the deck foam system shall not interfere with the simultaneous use of the fire main system.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.