46 CFR 42.25-20
§ 42.25-20 Computation for freeboard.
United States · 46 CFR — Shipping · Status: effective
Cite this
- Citation
- 46 CFR 42.25-20, § 42.25-20 Computation for freeboard, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/224710
- Permanent ID
ys:prov:224710@1- SHA-256
0f42c7341307b701a650b2cea735a72850ef9df7518fb0a8a2ff26ac96e9e819
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) The minimum summer freeboards must be computed in accordance with §§ 42.20-5 (a) and (b), 42.20-13, 42.20-15, 42.20-20, 42.20-25, 42.20-30, 42.20-35, 42.20-60, and 42.20-65, except that § 42.20-60 is modified by substituting the percentages in table 42.25-20(a) for those given in § 42.20-60:
Table 42.25-20(a)—Percentage of Deduction for Superstructure
[Total Effective Length of Superstructure]
(b) The winter timber freeboard shall be obtained by adding to the summer timber freeboard one thirty-sixth of the molded summer timber draft.
(c) The winter North Atlantic timber freeboard shall be the same as the winter North Atlantic freeboard prescribed in § 42.20-75(d)(1).
(d) The tropical timber freeboard shall be obtained by deducting from the summer timber freeboard one forty-eighth of the molded summer timber draft.
(e) The fresh water timber freeboard shall be computed in accordance with § 42.20-75(e) (1) or (2) based on the summer timber load waterline.