46 CFR 50.20-1
§ 50.20-1 General.
United States · 46 CFR — Shipping · Status: effective
Cite this
- Citation
- 46 CFR 50.20-1, § 50.20-1 General, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/224895
- Permanent ID
ys:prov:224895@1- SHA-256
71bf61ae7f0ad4578ada02b2fbbe0f26af6e3ce22281bf45ebaf8fc74970b8e3
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) The required vessel, equipment, or installation plans, as listed in this subchapter, are general in character, but include all plans which normally show the intended construction and safety features coming under the cognizance of the Coast Guard. In a particular case, however, not all of the plans enumerated may be applicable, and in such cases the Coast Guard will so notify the submitter.
(b) Manufacturers of pressure vessels and other components, which require specific fabrication inspection in accordance with the requirements of this subchapter, must submit and obtain approval of the applicable construction plans prior to the commencement of such fabrication. Manufacturers of automatically controlled boilers must submit and obtain approval of the applicable control system plans prior to installation of the boiler. Manufacturers of boilers which must meet the requirements of part 52 of this subchapter must submit the applicable construction plans for review prior to installation.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.