yourstate.us
46 CFR 160.133-23

§ 160.133-23 Procedure for approval of design, material, or construction change.

United States · 46 CFR — Shipping · Status: effective

Get this as JSONEmbed this
Cite this
Citation
46 CFR 160.133-23, § 160.133-23 Procedure for approval of design, material, or construction change, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/229457
Permanent ID
ys:prov:229457@1
SHA-256
31c89483ab65091b181370e0abefd92523941dbb0ad0a6b6bf84b6f10758d48e

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) Each change in design, material, or construction from the plans approved under 46 CFR 159.005-13 and § 160.133-13(h) of this subpart must be approved by the Commandant before being used in any production release mechanism. The manufacturer must submit any such change following the procedures set forth in § 160.133-9 of this subpart, but documentation on items that are unchanged from the plans approved under 46 CFR 159.005-13 and § 160.133-13(h) of this subpart need not be resubmitted. (b) Unless determined by the Commandant to be unnecessary, a prototype release mechanism with each change described in paragraph (a) of this section must be made and tested according to the procedures for new approvals in §§ 160.133-9 through 160.133-13 of this subpart. (c) Determinations of equivalence of design, material, or construction will be made by the Commandant only.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.