Colo. Rev. Stat. § 24-91-103.5

Public entity - contracts - delay clauses - definition

Colorado · Colorado Revised Statutes Title 24 — Government - State · Status: effective

Get this as JSONEmbed this
Cite this
Citation
Colo. Rev. Stat. § 24-91-103.5, Public entity - contracts - delay clauses - definition, Colorado, version 1 as recorded 2026-10-03, yourstate.us, https://yourstate.us/provision/2304604
Permanent ID
ys:prov:2304604@1
SHA-256
c7a46d389966ed3add0e8289311a2316f8d137899f155b958cb143a2cb21331d

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(1) (a) Any clause in a public works contract that purports to waive, release, or extinguish the rights of a contractor to recover costs or damages, or obtain an equitable adjustment, for delays in performing such contract, if such delay is caused in whole, or in part, by acts or omissions within the control of the contracting public entity or persons acting on behalf thereof, is against public policy and is void and unenforceable. (b) As used in this subsection (1), "public works contract" means a contract of the state, county, city and county, city, town, school district, special district, or any other political subdivision of the state for the construction, alteration, repair, or maintenance of any building, structure, highway, bridge, viaduct, pipeline, public works, real property as defined in section 24-30-1301 (15), or any other work dealing with construction, which includes, but need not be limited to, moving, demolition, or excavation performed in conjunction with such work. (2) Subsection (1) of this section is not intended to render void any contract provision of a public works contract that: (a) Precludes a contractor from recovering that portion of delay costs caused by the acts or omissions of the contractor or its agents; (b) Requires notice of any delay by the party responsible for such delay; (c) Provides for reasonable liquidated damages; (d) Provides for arbitration or any other procedure designed to settle contract disputes.