46 CFR 175.800
§ 175.800 Approved equipment and material.
United States · 46 CFR — Shipping · Status: effective
Cite this
- Citation
- 46 CFR 175.800, § 175.800 Approved equipment and material, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/230598
- Permanent ID
ys:prov:230598@1- SHA-256
ff075ab70f4e48e768c1d8fe6856689eea31155454c2886553c6c31018a3da26
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) Equipment and material that is required by this subchapter to be approved or of an approved type, must have been manufactured and approved in accordance with the design and testing requirements in subchapter Q (Equipment, Construction, and Materials: Specifications and Approval) of this chapter or as otherwise specified by the Commandant.
(b) Coast Guard publication COMDTINST M16714.3 (Series) “Equipment Lists, Items Approved, Certificated or Accepted under Marine Inspection and Navigation Laws” lists approved equipment by type and manufacturer. COMDTINST M16714.3 (Series) may be obtained from New Orders, Superintendent of Documents, P.O. Box 371954, Pittsburgh, PA 15250-7954.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.