At each initial and subsequent inspection for certification of a vessel, the owner or managing operator shall be prepared to conduct tests and have the vessel ready for inspections of machinery, fuel, and piping systems, including the following:
(a) Operation of the main propulsion machinery both ahead and astern;
(b) Operational test and inspection of engine control mechanisms including primary and alternate means of starting machinery;
(c) Inspection of all machinery essential to the routine operation of the vessel including generators and cooling systems;
(d) External inspection of fuel tanks and inspection of tank vents, piping, and pipe fittings;
(e) Inspection of all fuel system;
(f) Operational test of all valves in fuel lines by operating locally and at remote operating positions;
(g) Operational test of all overboard discharge and intake valves and watertight bulkhead pipe penetration valves;
(h) Operational test of the means provided for pumping bilges; and
(i) Test of machinery alarms including bilge high level alarms.