Utah Code § 38-10-102.1
Perfection of lien -- Notice of subcontractor's claim -- Information required to be provided -- Payments to be held in trust
Utah · Utah Code Title 38 — Liens · Status: effective
Cite this
- Citation
- Utah Code § 38-10-102.1, Perfection of lien -- Notice of subcontractor's claim -- Information required to be provided -- Payments to be held in trust, Utah, version 1 as recorded 2026-10-03, yourstate.us, https://yourstate.us/provision/2336559
- Permanent ID
ys:prov:2336559@1- SHA-256
260fbfc6d5b8d0fdae75412e3c2b87fece033b7eacdb626039f6837241fda82c
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(1)
(a) To perfect a lien a subcontractor must comply with the requirements of this section and Section 38-10-105.
(b) This section shall apply only to a subcontractor's claim or a portion of a claim for amounts more than $5,000, for work performed upon or materials or equipment furnished for each production unit.
(2) A subcontractor shall provide notice of a subcontractor's claim to the owner and operator designated by the owner within 20 days after the commencement of work or the furnishing of materials or equipment.
(3) The notice shall:
(a) be delivered, or mailed by certified mail, return receipt requested, to the:
(i) owner; and
(ii) operator designated by the owner;
(b) be considered delivered when deposited in the mail; and
(c) contain a statement setting forth the following information:
(i) identification of the lien claimant by full name, address, and telephone number;
(ii) the name of the person by whom the subcontractor was employed or to whom the subcontractor furnished material or equipment; and
(iii) a description of the property comprising the production unit.
(4) Failure to deliver or mail the notice shall discharge and satisfy the lien attaching to the interest of the owner to the extent the owner pays a contractor or operator the contractor's or operator's share of all, or part, of the lien claimant's agreed contract price.
(5)
(a) Any contractor or subcontractor shall provide, in writing, to each person with whom the contractor or subcontractor contracts:
(i) the full name and address of the:
(A) owner of the production unit; and
(B) the operator designated by the owner; and
(ii) a description of the property comprising the production unit.
(b) Failure to provide the information required under this section within three days after the work is commenced or the materials and equipment are furnished shall entitle the claimant to an award of costs and attorney fees in an action against the person to enforce the contract.
(6) Any contractor, operator, or subcontractor who receives payment for work performed upon, or material or equipment furnished for any production unit, shall hold all payments in trust for the person with whom the contractor, operator, or subcontractor contracts for work upon, or the furnishing of materials or equipment for the production unit, for any amount remaining unpaid under the contract.