Utah Code § 54-26-402
Alternative service requirements
Utah · Utah Code Title 54 — Public Utilities · Status: effective
Cite this
- Citation
- Utah Code § 54-26-402, Alternative service requirements, Utah, version 1 as recorded 2026-10-03, yourstate.us, https://yourstate.us/provision/2341827
- Permanent ID
ys:prov:2341827@1- SHA-256
d6df428cc9a3188c4558e29de148b3d7343016a112b6781c562e8435a0e0acea
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(1) A large load customer may enter into a large load contract with a large-scale generation provider if:
(a) a qualified electric utility fails to complete an evaluation or provide a written response within the time period specified in Section 54-26-202; or
(b) the qualified electric utility and large load customer cannot agree to a large load contract within 90 days after the day on which the large load customer receives the evaluation described in Section 54-26-202, unless the qualified electric utility and the large load customer mutually agree to a longer period of time.
(2) After submitting a large-scale service request, a large load customer:
(a) may negotiate a contract with one or more large-scale generation providers; and
(b) may not execute a contract with a large-scale generation provider unless the conditions described in Subsection (1) are met.