Utah Code § 63G-6a-1206

Rules to determine allowable incurred costs -- Required information

Utah · Utah Code Title 63G — General Government · Status: effective

Get this as JSONEmbed this
Cite this
Citation
Utah Code § 63G-6a-1206, Rules to determine allowable incurred costs -- Required information, Utah, version 1 as recorded 2026-10-03, yourstate.us, https://yourstate.us/provision/2347375
Permanent ID
ys:prov:2347375@1
SHA-256
8d5538308fdabc710b3e4a3a4b9e3ad14061af60cf1412d05461627eef36a713

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(1) (a) A rulemaking authority may, by rule, establish the cost principles to be included in a cost-reimbursement contract to determine incurred costs for the purpose of calculating a reimbursement. (b) The cost principles established by rule under Subsection (1)(a) may be modified, by contract, if the procurement official approves the modification. (2) Except as provided in Subsection (5), a person who seeks to be, or is, a party in a cost-based contract with a procurement unit shall: (a) submit cost or pricing data relating to determining the cost or pricing amount; and (b) certify that, to the best of the contractor's knowledge and belief, the cost or pricing data submitted is accurate and complete as of the date specified by the procurement unit. (3) The procurement official shall ensure that the date specified under Subsection (2)(b) is before: (a) the pricing of any contract awarded by a standard procurement process or pursuant to a sole source procurement, if the total contract price is expected to exceed an amount established by rule made by the rulemaking authority; or (b) the pricing of any change order that is expected to exceed an amount established by rule made by the rulemaking authority. (4) A contract or change order that requires a certification described in Subsection (2) shall include a provision that the price to the procurement unit, including profit or fee, shall be adjusted to exclude any significant sums by which the procurement unit finds that the price was increased because the contractor provided cost or pricing data that was inaccurate, incomplete, or not current as of the date specified by the procurement officer. (5) A procurement unit is not required to comply with Subsection (2) if: (a) the contract price is based on adequate price competition; (b) the contract price is based on established catalogue prices or market prices; (c) the contract price is set by law or rule; or (d) the procurement states, in writing: (i) that, in accordance with rules made by the rulemaking authority, the requirements of Subsection (2) may be waived; and (ii) the reasons for the waiver.