Utah Code § 63G-6a-1207

Certification of change order

Utah · Utah Code Title 63G — General Government · Status: effective

Get this as JSONEmbed this
Cite this
Citation
Utah Code § 63G-6a-1207, Certification of change order, Utah, version 1 as recorded 2026-10-03, yourstate.us, https://yourstate.us/provision/2347378
Permanent ID
ys:prov:2347378@1
SHA-256
91fb9e1ca26885f9ce6f56a42ee37da216d891ef55e014ff6de600d9d62b549d

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(1) Under a construction contract, a change order that increases the contract amount may not be made without prior written certification that the change order is within the determined project or contract budget by: (a) the fiscal officer of the entity responsible for funding the project or contract; or (b) the official responsible for monitoring and reporting upon the status of the costs of the total project or contract budget. (2) If a change order will result in an increase in the total project or contract budget, the change order may not be made, unless: (a) sufficient funds are added to the project contract or budget; or (b) the scope of the project or contract is adjusted to permit the degree of completion feasible within the total project or contract budget as it existed before the change order under consideration. (3) Notwithstanding any other provision of this section, it shall be presumed that this section has been complied with if the contractor reasonably relies on an executed change order.