W. Va. Code § 24-2-1e

Rate recovery for construction of electric transmission facilities

West Virginia · West Virginia Code Chapter 24 — Public Service Commission · Status: effective

Get this as JSONEmbed this
Cite this
Citation
W. Va. Code § 24-2-1e, Rate recovery for construction of electric transmission facilities, West Virginia, version 1 as recorded 2026-10-03, yourstate.us, https://yourstate.us/provision/2376970
Permanent ID
ys:prov:2376970@1
SHA-256
e54e683b326e44b309117da0da6b0e51e902c751b5f57f5afe8f6739b9b07a57

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

In order to encourage the construction of transmission facilities necessary to transmit electric power from generating facilities located in this state to areas where such power can be economically marketed, the commission may allow an electric utility accelerated rate recovery for transmission facilities constructed or upgraded for the purpose of increasing the capacity to transmit electric power to areas outside the utility's service territory where such power can be economically marketed. In allowing accelerated rate recovery, the commission shall include the impact of the investment in transmission facilities on any investment equalization agreement in which the utilities participate.