48 CFR 4.1003
4.1003 Establishing line items.
United States · 48 CFR — Federal Acquisition Regulations System · Status: effective
Cite this
- Citation
- 48 CFR 4.1003, 4.1003 Establishing line items, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/239128
- Permanent ID
ys:prov:239128@1- SHA-256
bc5400d2e82406fd80e0dcc8ff7857565f42b7751ee235ac154652ab720a7681
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
Establish separate line items for deliverables that have the following characteristics except as provided at 4.1005-2:
(a) Separately identifiable.
(1) A supply is separately identifiable if it has its own identification (e.g., national stock number (NSN), item description, manufacturer's part number).
(2) Services are separately identifiable if they have no more than one statement of work or performance work statement.
(3) If the procurement instrument involves a first article (see subpart 9.3), establish a separate line item for each item requiring a separate approval. If the first article consists of a lot composed of a mixture of items that will be approved as a single lot, a single line item may be used.
(b) Single unit price or total price.
(c) Single accounting classification citation. A single deliverable may be funded by multiple accounting classifications when the deliverable effort cannot be otherwise subdivided.
(d) Separate delivery schedule, destination, period of performance, or place of performance.
(e) Single contract pricing type (e.g., fixed-price or cost-reimbursement).
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.