48 CFR 14.202-1
14.202-1 Bidding time.
United States · 48 CFR — Federal Acquisition Regulations System · Status: effective
Cite this
- Citation
- 48 CFR 14.202-1, 14.202-1 Bidding time, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/239688
- Permanent ID
ys:prov:239688@1- SHA-256
87b45e7ae4835c6d628e2b01204e50e58d4e099a985ebb8da9174ed2d3abbe7f
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) Policy. A reasonable time for prospective bidders to prepare and submit bids shall be allowed in all invitations, consistent with the needs of the Government. (For construction contracts, see 36.213-3(a).) A bidding time (i.e., the time between issuance of the solicitation and opening of bids) of at least 30 calendar days shall be provided when synopsis is required by subpart 5.2.
(b) Factors to be considered. Because of unduly limited bidding time, some potential sources may be precluded from bidding and others may be forced to include amounts for contingencies that, with additional time, could be eliminated. To avoid unduly restricting competition or paying higher-than-necessary prices, consideration shall be given to such factors as the following in establishing a reasonable bidding time:
(1) degree of urgency;
(2) complexity of requirement;
(3) anticipated extent of subcontracting;
(4) whether use was made of presolicitation notices;
(5) geographic distribution of bidders; and (6) normal transmittal time for both invitations and bids.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.