48 CFR 16.206-2
16.206-2 Application.
United States · 48 CFR — Federal Acquisition Regulations System · Status: effective
Cite this
- Citation
- 48 CFR 16.206-2, 16.206-2 Application, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/239869
- Permanent ID
ys:prov:239869@1- SHA-256
4bf31b6191ec246b4efcc1fe5138ec9d2bdf6d301742af85902eaaadf637cd49
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
A fixed-ceiling-price contract with retroactive price redetermination is appropriate for research and development contracts estimated at the simplified acquisition threshold or less when it is established at the outset that a fair and reasonable firm fixed price cannot be negotiated and that the amount involved and short performance period make the use of any other fixed-price contract type impracticable.
(a) A ceiling price shall be negotiated for the contract at a level that reflects a reasonable sharing of risk by the contractor. The established ceiling price may be adjusted only if required by the operation of contract clauses providing for equitable adjustment or other revision of the contract price under stated circumstances.
(b) The contract should be awarded only after negotiation of a billing price that is as fair and reasonable as the circumstances permit.
(c) Since this contract type provides the contractor no cost control incentive except the ceiling price, the contracting officer should make clear to the contractor during discussion before award that the contractor's management effectiveness and ingenuity will be considered in retroactively redetermining the price.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.