yourstate.us
48 CFR 19.815

19.815 Release and notification requirements for non-8(a) procurement.

United States · 48 CFR — Federal Acquisition Regulations System · Status: effective

Get this as JSONEmbed this
Cite this
Citation
48 CFR 19.815, 19.815 Release and notification requirements for non-8(a) procurement, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/240128
Permanent ID
ys:prov:240128@1
SHA-256
91ee77b1e7d7a5a5bdb7755dcfae6ac3087ba1a48f45600d0e93a958f3b13745

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) Once a requirement has been accepted by SBA into the 8(a) program, any follow-on requirements (see definition at 13 CFR 124.3) shall remain in the 8(a) program unless— (1) SBA agrees to release the requirement from the 8(a) program for a follow-on, non-8(a) procurement in accordance with 13 CFR 124.504(d) (see paragraph (b) of this section); or (2) There is a mandatory source (see 8.002 or 8.003; also see paragraph (f) of this section). (b) To obtain release of a requirement for a follow-on, non-8(a) procurement, (other than a mandatory source listed at 8.002 or 8.003), the contracting officer shall make a written request to, and receive concurrence from, the SBA Associate Administrator for Business Development. (c)(1) The written request to the SBA Associate Administrator for Business Development shall indicate— (i) Whether the agency has achieved its small disadvantaged business goal; (ii) Whether the agency has achieved its HUBZone, SDVOSB, WOSB, or small business goal(s); and (iii) Whether the requirement is critical to the business development of the 8(a) contractor that is currently performing the requirement. (2) Generally, a requirement that was previously accepted into the 8(a) program will only be released for procurements outside the 8(a) program when the contracting activity agency agrees to set aside the requirement under the small business, HUBZone, SDVOSB, or WOSB programs. (3) The requirement that a follow-on procurement must be released from the 8(a) program in order for it to be fulfilled outside the 8(a) program does not apply to task or delivery orders offered to and accepted into the 8(a) program, where the basic contract was not accepted into the 8(a) program. (d)(1) When a contracting officer decides that a requirement previously procured under the 8(a) program is a new requirement and not a follow-on requirement to an 8(a) contract(s), the contracting officer shall coordinate with and submit a written notice to the SBA District Office servicing the 8(a) incumbent firm and to the SBA procurement center representative (or, if a procurement center representative is not assigned, see 19.402(a)) indicating that the agency intends to procure the requirement outside the 8(a) program (see 19.810(a)(4)). (2) The written notice shall include a copy of the acquisition plan, if available; the performance work statement (PWS), statement of work (SOW), or statement of objectives (SOO) for the new contract requirement; and the values of the existing 8(a) contract(s) and the new contract requirement. (e)(1) When a contracting officer decides to procure a follow-on requirement to an 8(a) contract using an existing, limited competition contracting vehicle that is not available to all 8(a) participants, and the current or previous 8(a) contract was available to all 8(a) participants, the contracting officer shall coordinate with and submit a written notice to the SBA District Office servicing the 8(a) incumbent firm and to the SBA procurement center representative (or, if a procurement center representative is not assigned, see 19.402(a)) indicating the intent to do so. (2) The written notice shall include a copy of the acquisition plan, if available; the PWS, SOW, or SOO for the new contract requirement; and the values of both contracts. (f)(1) When a mandatory source will be used for a follow-on requirement to an 8(a) contract, the contracting officer should submit a written notice to the SBA Associate Administrator for Business Development of the intent to do so at least 30 days prior to the end of the contract or order in accordance with 13 CFR 124.504(d)(4)(ii). (2) The written notice should include a written determination that a mandatory source will be used to fulfill the requirement.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.