25.605 Evaluating offers of foreign construction material.

United States · 48 CFR — Federal Acquisition Regulations System · Status: effective

Get this as JSONEmbed this
Cite this
Citation
48 CFR 25.605, 25.605 Evaluating offers of foreign construction material, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/240508
Permanent ID
ys:prov:240508@1
SHA-256
111782bfe6fd252aab1c05ae8aa6f675702e82f5322d99928b0ab2f77c93d9b6

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) If the contracting officer has determined that an exception applies because the cost of certain domestic construction material is unreasonable, in accordance with section 25.604, then the contracting officer shall apply evaluation factors to the offer incorporating the use of such foreign construction material as follows: (1) Use an evaluation factor of 25 percent, applied to the total offered price of the contract, if foreign manufactured construction material is incorporated in the offer based on an exception for unreasonable cost of comparable domestic construction material requested by the offeror. (2) In addition, use an evaluation factor of 20 percent applied to the cost of foreign unmanufactured construction material incorporated in the offer based on an exception for unreasonable cost of comparable domestic unmanufactured construction material requested by the offeror. (3) Total evaluated price = offered price + (.25 × offered price, if (a)(1) applies) + (.20 × cost of foreign unmanufactured construction material, if (a)(2) applies). (b) If the solicitation specifies award on the basis of factors in addition to cost or price, apply the evaluation factors as specified in paragraph (a) of this section and use the evaluated price in determining the offer that represents the best value to the Government. (c) Unless paragraph (b) applies, if two or more offers are equal in price, the contracting officer must give preference to an offer that does not include foreign construction material excepted at the request of the offeror on the basis of unreasonable cost. (d) Offerors also may submit alternate offers based on use of equivalent domestic construction material to avoid possible rejection of the entire offer if the Government determines that an exception permitting use of a particular foreign construction material does not apply. (e) If the contracting officer awards a contract to an offeror that proposed foreign construction material not listed in the applicable clause in the solicitation (paragraph (b)(3) of 52.225-21, or paragraph (b)(3) of 52.225-23), the contracting officer must add the excepted materials to the list in the contract clause.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.