48 CFR 32.110
32.110 Payment of subcontractors under cost-reimbursement prime contracts.
United States · 48 CFR — Federal Acquisition Regulations System · Status: effective
Cite this
- Citation
- 48 CFR 32.110, 32.110 Payment of subcontractors under cost-reimbursement prime contracts, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/240902
- Permanent ID
ys:prov:240902@1- SHA-256
dce61ad51e9c62e38f4db3c19d3285eeb6f6a003ff3f72d08df427441154a219
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
If the contractor makes financing payments to a subcontractor under a cost-reimbursement prime contract, the contracting officer should accept the financing payments as reimbursable costs of the prime contract only under the following conditions:
(a) The payments are made under the criteria in subpart 32.5 for customary progress payments based on costs, 32.202-1 for commercial product or commercial service purchase financing, or 32.1003 for performance-based payments, as applicable.
(b) If customary progress payments are made, the payments do not exceed the progress payment rate in 32.501-1, unless unusual progress payments to the subcontractor have been approved in accordance with 32.501-2.
(c) If customary progress payments are made, the subcontractor complies with the liquidation principles of 32.503-8, 32.503-9, and 32.503-10.
(d) If performance-based payments are made, the subcontractor complies with the liquidation principles of 32.1004(d).
(e) The subcontract contains financing payments terms as prescribed in this part.