32.609 Delays in receipt of notices or demands.

United States · 48 CFR — Federal Acquisition Regulations System · Status: effective

Get this as JSONEmbed this
Cite this
Citation
48 CFR 32.609, 32.609 Delays in receipt of notices or demands, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/241000
Permanent ID
ys:prov:241000@1
SHA-256
b741024a21216cf0ad5ed70ca748e7191dbb79d837876840464b84b5947f22ce

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

If interest is accrued based on the date of the demand letter and delivery of the demand letter is delayed by the Government (e.g., undue delay after dating at the originating office or delays in the mail), the date of the debt and accrual of interest shall be extended to a time that is fair and reasonable under the particular circumstances.