52.211-12 Liquidated Damages—Construction.
United States · 48 CFR — Federal Acquisition Regulations System · Status: effective
Cite this
- Citation
- 48 CFR 52.211-12, 52.211-12 Liquidated Damages—Construction, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/242004
- Permanent ID
ys:prov:242004@1- SHA-256
adb71beafc68fc54076318cd426594305cc50a7d27878fc43781939107ed57d8
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
As prescribed in 11.503(b), insert the following clause in solicitations and contracts:
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of __ [Contracting Officer insert amount] for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.