48 CFR 52.247-59
52.247-59 F.o.b. Origin—Carload and Truckload Shipments.
United States · 48 CFR — Federal Acquisition Regulations System · Status: effective
Cite this
- Citation
- 48 CFR 52.247-59, 52.247-59 F.o.b. Origin—Carload and Truckload Shipments, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/242539
- Permanent ID
ys:prov:242539@1- SHA-256
bec003d56bc05f171b330af018d3707cf77e3404030e83ef1eec1538a65fe425
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
As prescribed in 47.305-16(a), insert the following clause in solicitations and contracts when it is contemplated that they may result in f.o.b. origin contracts with shipments in carloads or truckloads. This will facilitate realistic freight cost evaluations of offers and ensure that contractors produce economical shipments of agreed size.
(a) The Contractor agrees that shipment shall be made in carload or truckload lots when the quantity to be delivered to any one destination in any delivery period pursuant to the contract schedule of deliveries is sufficient to constitute a carload r truckload shipment, except as may otherwise be permitted or directed, in writing, by the Contracting Officer.
(b) For evaluation purposes, the agreed weight of a carload or truckload shall be the highest applicable minimum weight that will result in the lowest freight rate (or per car charge) on file or published in common carrier tariffs or tenders as of the date of bid opening (or the closing date specified for receipt of proposals).
(c) For purposes of actual delivery, the agreed weight of a carload or truckload will be the highest applicable minimum weight that will result in the lowest possible freight rate (or per car charge) on file or published as of date of shipment.
(d) If the total weight of any scheduled quantity to a destination is less than the highest carload/truckload minimum weight used for evaluation of offers, the Contractor agrees to ship such scheduled quantity in one shipment.
(e) The Contractor shall be liable to the Government for any increased costs to the Government resulting from failure to comply with the above requirements.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.