48 CFR 217.7404
217.7404 Limitations.
United States · 48 CFR — Federal Acquisition Regulations System · Status: effective
Cite this
- Citation
- 48 CFR 217.7404, 217.7404 Limitations, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/243272
- Permanent ID
ys:prov:243272@1- SHA-256
ca3b01dcac80ccb57a11fed9f66c95535fb20101d91ad5b2c87186e1be8ca74c
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
See PGI 217.7404 for additional guidance on obtaining approval to authorize use of an undefinitized contact action, documentation requirements, and other limitations on their use.
(a) Foreign military sales contracts.
(1) A contracting officer may not enter into a UCA for a foreign military sale unless—
(i) The UCA provides for agreement upon contractual terms, specifications, and price by the end of the 180-day period beginning on the date on which the contractor submits a qualifying proposal; and
(ii) The contracting officer obtains approval from the head of the contracting activity to enter into a UCA in accordance with 217.7404-1.
(2) The head of the contracting activity may waive the requirements of paragraph (a)(1) of this section, if a waiver is necessary in order to support any of the following operations:
(i) A contingency operation.
(ii) A humanitarian or peacekeeping operation.
(b) Unilateral definitization by a contracting officer. Any UCA with a value greater than $50 million may not be unilaterally definitized until—
(1) The earlier of—
(i) The end of the 180-day period, beginning on the date on which the contractor submits a qualifying proposal to definitize the contractual terms, specifications, and price; or
(ii) The date on which the amount of funds expended under the contractual action is equal to more than 50 percent of the negotiated overall not-to-exceed price for the contractual action;
(2) The head of the contracting activity, without power of redelegation, approves the definitization in writing;
(3) The contracting officer provides a copy of the written approval to the contractor; and
(4) A period of 30 calendar days has elapsed after the written approval is provided to the contractor.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.