48 CFR 217.7404-4

217.7404-4 Limitations on obligations.

United States · 48 CFR — Federal Acquisition Regulations System · Status: effective

Get this as JSONEmbed this
Cite this
Citation
48 CFR 217.7404-4, 217.7404-4 Limitations on obligations, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/243276
Permanent ID
ys:prov:243276@1
SHA-256
dd9cf79c73166997949f2e9e2710856a02461b0d7f4180c76ef33f9152b30a52

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) The Government shall not obligate more than 50 percent of the not-to-exceed price before definitization. However, if a contractor submits a qualifying proposal before 50 percent of the not-to-exceed price has been obligated by the Government, then the limitation on obligations before definitization may be increased to no more than 75 percent (see 232.102-70 for coverage on provisional delivery payments). (b) In determining the appropriate amount to obligate, the contracting officer shall assess the contractor's proposal for the undefinitized period and shall obligate funds only in an amount consistent with the contractor's requirements for the undefinitized period.