48 CFR 242.1204
242.1204 Applicability of novation agreements.
United States · 48 CFR — Federal Acquisition Regulations System · Status: effective
Cite this
- Citation
- 48 CFR 242.1204, 242.1204 Applicability of novation agreements, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/244278
- Permanent ID
ys:prov:244278@1- SHA-256
22138c062f99fe089bbe4986208dc60919de19272991f8960c4fd7483d042076
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(i) When a novation agreement is required and the transferee intends to incur restructuring costs as defined at 213.205-70, the cognizant contracting officer shall include the following provision as paragraph (b)(7) of the novation agreement instead of the paragraph (b)(7) provided in the sample format at FAR 42.1204(i):
“(7)(i) Except as set forth in subparagraph (7)(ii) below, the Transferor and the Transferee agree that the Government is not obligated to pay or reimburse either of them for, or otherwise give effect to, any costs, taxes, or other expenses, or any related increases, directly or indirectly arising out of or resulting from the transfer or this Agreement, other than those that the Government in the absence of this transfer or Agreement would have been obligated to pay or reimburse under the terms of the contracts.
(ii) The Government recognizes that restructuring by the Transferee incidental to the acquisition/merger may be in the best interests of the Government. Restructuring costs that are allowable under Part 31 of the Federal Acquisition Regulation (FAR) or Part 231 of the Defense Federal Acquisition Regulation Supplement (DFARS) may be reimbursed under flexibily-priced novated contracts, provided the Transferee demonstrates that the restructuring will reduce overall costs to the Department of Defense (DoD) (and to the National Aeronautics and Space Administration (NASA), where there is a mix of DoD and NASA contracts), and the requirements included in DFARS 231.205-70 are met. Restructuring costs shall not be allowed on novated contracts unless there is an audit of the restructuring proposal; a determination by the contracting officer of overall reduced costs to DoD/NASA; and an Advance Agreement setting forth a cumulative cost ceiling for restructuring projects and the period to which such costs shall be assigned.”
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.