48 CFR 242.7202
242.7202 Policy.
United States · 48 CFR — Federal Acquisition Regulations System · Status: effective
Cite this
- Citation
- 48 CFR 242.7202, 242.7202 Policy, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/244289
- Permanent ID
ys:prov:244289@1- SHA-256
5c2cb3f4917ca3e49e1e45e4249746cfd150e04b6c5066ee6f2b453ed5682b08
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) DoD policy is for its contractors to have an MMAS that conforms to the standards in paragraph (d) of the clause at 252.242-7004, Material Management and Accounting System, so that the system—
(1) Reasonably forecasts material requirements;
(2) Ensures the costs of purchased and fabricated material charged or allocated to a contract are based on valid time-phased requirements; and
(3) Maintains a consistent, equitable, and unbiased logic for costing of material transactions.
(b) The cognizant contracting officer, in consultation with the auditor and functional specialist, if appropriate, shall—
(1) Determine the acceptability of the contractor's MMAS and approve or disapprove the system; and
(2) Pursue correction of any weaknesses or deficiencies.
(c) In evaluating the acceptability of the contractor's MMAS, the contracting officer, in consultation with the auditor and functional specialist, if appropriate, shall determine whether the contractor's MMAS complies with the system criteria for an acceptable MMAS as prescribed in the clause at 252.242-7004, Material Management and Accounting System.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.