48 CFR 252.216-7003
252.216-7003 Economic price adjustment—wage rates or material prices controlled by a foreign government.
United States · 48 CFR — Federal Acquisition Regulations System · Status: effective
Cite this
- Citation
- 48 CFR 252.216-7003, 252.216-7003 Economic price adjustment—wage rates or material prices controlled by a foreign government, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/244577
- Permanent ID
ys:prov:244577@1- SHA-256
a1ae8c640270696c801005796cd8f51cebd48be16e330f706566ed9fab15fa41
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
As prescribed in 216.203-4-70(c)(1), use the following clause:
(a) As represented by the Contractor in its offer, the prices set forth in this contract—
(1) Are based on the wage rates or material prices established and controlled by the government of the country specified by the Contractor in its offer; and
(2) Do not include contingency allowances to pay for possible increases in wage rates or material prices.
(b) If wage rates or material prices are revised by the government named in paragraph (a) of this clause, the Contracting Officer shall make an equitable adjustment in the contract price and shall modify the contract to the extent that the Contractor's actual costs of performing this contract are increased or decreased, as a direct result of the revision, subject to the following:
(1) For increases in established wage rates or material prices, the increase in contract unit price(s) shall be effective on the same date that the government named in paragraph (a) of this clause increased the applicable wage rate(s) or material price(s), but only if the Contracting Officer receives the Contractor's written request for contract adjustment within 10 days of the change. If the Contractor's request is received later, the effective date shall be the date that the Contracting Officer received the Contractor's request.
(2) For decreases in established wage rates or material prices, the decrease in contract unit price(s) shall be effective on the same date that the government named in paragraph (a) of this clause decreased the applicable wage rate(s) or material price(s). The decrease in contract unit price(s) shall apply to all items delivered on and after the effective date of the government's rate or price decrease.
(c) No modification changing the contract unit price(s) shall be executed until the Contracting Officer has verified the applicable change in the rates or prices set by the government named in paragraph (a) of this clause. The Contractor shall make available its books and records that support a requested change in contract price.
(d) Failure to agree to any adjustment shall be a dispute under the Disputes clause of this contract.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.