48 CFR 552.238-93
552.238-93 Order Acknowledgement.
United States · 48 CFR — Federal Acquisition Regulations System · Status: effective
Cite this
- Citation
- 48 CFR 552.238-93, 552.238-93 Order Acknowledgement, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/245994
- Permanent ID
ys:prov:245994@1- SHA-256
44c67a0b38b098921af7f1e4aa784be88c23f6e0c3b83bc94376c86a8385b71d
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
As prescribed in 538.273(d)(17), insert the following clause:
Contractors shall acknowledge only those orders which state “Order Acknowledgement Required.” These orders shall be acknowledged within 10 calendar days after receipt. Such acknowledgement shall be sent to the ordering activity placing the order and contain information pertinent to the order, including the anticipated delivery date.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.