48 CFR 742.1170-4
742.1170-4 Progress reporting requirements and contract clause.
United States · 48 CFR — Federal Acquisition Regulations System · Status: effective
Cite this
- Citation
- 48 CFR 742.1170-4, 742.1170-4 Progress reporting requirements and contract clause, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/246994
- Permanent ID
ys:prov:246994@1- SHA-256
1a887d582595cf466886feedb4fae2923f709e205cc8ae355b84659cca1291c6
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) When the requiring office needs information on contract performance status on a regular basis, the contracting officer may require the contractor to submit periodic progress reports, tailored to address specific contract requirements but limited to only that information essential to USAID's needs in monitoring the contractor's progress.
(b) Because the contracting officer's representative is the individual most familiar with the contractor's performance, the contractor must submit the progress reports directly to the cognizant technical officer. The contracting officer's representative must review the reports and advise the contracting officer, in writing, of any recommended action, including any action needed to address potential or actual delays in performance. The contracting officer's representative must so advise the contracting officer in sufficient time, typically thirty days, for him or her to take any action that the contracting officer determines is appropriate. The requirements of this paragraph do not relieve the contractor of notification requirements identified elsewhere in the contract.
(c) The contracting officer must insert the clause at 752.242-70, Periodic Progress Reports, in solicitations and contracts that require progress reporting, as specified in this section. The contracting officer must include specific reporting instructions in the Schedule.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.