yourstate.us
48 CFR 952.204-78

952.204-78 DOE Directives.

United States · 48 CFR — Federal Acquisition Regulations System · Status: effective

Get this as JSONEmbed this
Cite this
Citation
48 CFR 952.204-78, 952.204-78 DOE Directives, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/248284
Permanent ID
ys:prov:248284@1
SHA-256
aa3ff3dfca7878e81bfa8d14f0187b83b6f96890d2350372feaad7496b65f43d

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

As prescribed in 904.7301, insert the following clause: (a) In performing work under this contract, the Contractor shall comply with the requirements of Department of Energy Directives, or parts thereof, identified in the List of Applicable Directives appended to this contract, identified in the Statement of Work or identified in a special clause within this contract. The Contracting Officer may revise the list of applicable Directives by bilateral modification to the contract. Prior to the modification, the Contracting Officer shall notify the Contractor in writing of DOE's intent and provide the contractor with the opportunity to: assess the impact on cost, funding, technical performance, and schedule; and identify any potential inconsistencies between the revised list and the other terms and conditions of the contract. Within 30 days of being notified, the Contractor shall advise the Contracting Officer in writing of the potential impact of the modification. The Contracting Officer and Contractor shall decide whether or not to proceed with the modification. Before executing the modification, they must agree to any appropriate changes to other contract terms and conditions, including cost and schedule, pursuant to the clause of this contract entitled “Changes.” (b) Regardless of the performer of the work, the Contractor is responsible for compliance with the requirements of this clause. The Contractor is responsible for flowing down the requirements of this clause to subcontracts at any tier to the extent necessary to ensure the contractor's compliance with the requirements.