Or. Rev. Stat. § 279C.515

Conditions concerning payment of claims by public officers, payment to persons furnishing labor or materials and complaints

Oregon · Oregon Revised Statutes Chapter 279C — Public Contracting - Public Improvements and Related Contracts · Status: effective

Get this as JSONEmbed this
Cite this
Citation
Or. Rev. Stat. § 279C.515, Conditions concerning payment of claims by public officers, payment to persons furnishing labor or materials and complaints, Oregon, version 1 as recorded 2026-10-04, yourstate.us, https://yourstate.us/provision/2490385
Permanent ID
ys:prov:2490385@1
SHA-256
52d1256556d7d6bcd3eaf6ef8ec413c523a8c9321d1c21156b48f8849eda20e3

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(1) Every public improvement contract must contain a clause or condition that, if the contractor fails, neglects or refuses to pay promptly a person’s claim for labor or services that the person provides to the contractor or a subcontractor in connection with the public improvement contract as the claim becomes due, the proper officer that represents the state or a county, school district, municipality or municipal corporation or a subdivision of the state, county, school district, municipality or municipal corporation may pay the amount of the claim to the person that provides the labor or services and charge the amount of the payment against funds due or to become due the contractor by reason of the contract. (2) Every public improvement contract must contain a clause or condition that, if the contractor or a first-tier subcontractor fails, neglects or refuses to pay a person that provides labor or materials in connection with the public improvement contract within 30 days after receiving payment from the contracting agency or a contractor, the contractor or first-tier subcontractor owes the person the amount due plus interest charges that begin at the end of the 10-day period within which payment is due under ORS 279C.580 (4) and that end upon final payment, unless payment is subject to a good faith dispute as defined in ORS 279C.580. The rate of interest on the amount due is nine percent per annum. The amount of interest may not be waived. (3) Every public improvement contract and every contract related to the public improvement contract must contain a clause or condition that, if the contractor or a subcontractor fails, neglects or refuses to pay a person that provides labor or materials in connection with the public improvement contract, the person may file a complaint with the Construction Contractors Board, unless payment is subject to a good faith dispute as defined in ORS 279C.580. (4) Paying a claim in the manner authorized in this section does not relieve the contractor or the contractor’s surety from obligation with respect to an unpaid claim.