Or. Rev. Stat. § 279C.545
Time limitation on claim for overtime; posting of circular by contractor
Oregon · Oregon Revised Statutes Chapter 279C — Public Contracting - Public Improvements and Related Contracts · Status: effective
Cite this
- Citation
- Or. Rev. Stat. § 279C.545, Time limitation on claim for overtime; posting of circular by contractor, Oregon, version 1 as recorded 2026-10-04, yourstate.us, https://yourstate.us/provision/2490397
- Permanent ID
ys:prov:2490397@1- SHA-256
e6cb4ca31530946991b7544cc41e334f35c219c0f66232df60370a3a1442af5b
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
When labor is employed by the state or a county, school district, municipality, municipal corporation or subdivision thereof through another as a contractor, any worker employed by the contractor shall be foreclosed from the right to collect for any overtime provided in ORS 279C.540 unless a claim for payment is filed with the contractor within 90 days from the completion of the contract, providing the contractor has:
(1) Caused a circular clearly printed in boldfaced 12-point type and containing a copy of this section to be posted in a prominent place alongside the door of the timekeeper’s office or in a similar place that is readily available and freely visible to workers employed on the work.
(2) Maintained the circular continuously posted from the inception to the completion of the contract on which workers are or have been employed. [2003 c.794 §145]
(Retainage and Payments)