48 CFR 1252.217-79
1252.217-79 Delays.
United States · 48 CFR — Federal Acquisition Regulations System · Status: effective
Cite this
- Citation
- 48 CFR 1252.217-79, 1252.217-79 Delays, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/249113
- Permanent ID
ys:prov:249113@1- SHA-256
aea7ac19ed43c611af9d0ee67659779bf3ae4ba4cea6cc8bd7003bd5b4fcb49d
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
As prescribed at 1217.7001(b), insert the following clause:
When during the performance of this contract the Contractor is required to delay work on a vessel temporarily, due to orders or actions of the Government respecting stoppage of work to permit shifting the vessel, stoppage of hot work to permit bunkering, stoppage of work due to embarking or debarking passengers and loading or discharging cargo, and the Contractor is not given sufficient advance notice or is otherwise unable to avoid incurring additional costs on account thereof, an equitable adjustment shall be made in the price of the contract pursuant to the “Changes” clause.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.