1252.222-70 Strikes or Picketing Affecting Timely Completion of the Contract Work.

United States · 48 CFR — Federal Acquisition Regulations System · Status: effective

Get this as JSONEmbed this
Cite this
Citation
48 CFR 1252.222-70, 1252.222-70 Strikes or Picketing Affecting Timely Completion of the Contract Work, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/249115
Permanent ID
ys:prov:249115@1
SHA-256
3d8da37b14c5e4f326cee76b1876362bee479876cde845943c5f4c86c98b4a95

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

As prescribed in 1222.101-71(a), insert the following clause: Notwithstanding any other provision hereof, the Contractor is responsible for delays arising out of labor disputes, including but not limited to strikes, if such strikes are reasonably avoidable. A delay caused by a strike or by picketing which constitutes an unfair labor practice is not excusable unless the Contractor takes all reasonable and appropriate action to end such a strike or picketing, such as the filing of a charge with the National Labor Relations Board, the use of other available Government procedures, and the use of private boards or organizations for the settlement of disputes.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.