Or. Rev. Stat. § 459A.321
Approval of electronics producer responsibility plan
Oregon · Oregon Revised Statutes Chapter 459A — Reuse and Recycling · Status: effective
Cite this
- Citation
- Or. Rev. Stat. § 459A.321, Approval of electronics producer responsibility plan, Oregon, version 1 as recorded 2026-10-04, yourstate.us, https://yourstate.us/provision/2513337
- Permanent ID
ys:prov:2513337@1- SHA-256
983b32e34978e827d9eb0bfa01cd030b3e1616a871c6db15c0e2a01fb75daca4
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(1) The Department of Environmental Quality shall approve an electronics producer responsibility program plan as provided in this section if the department determines that the plan satisfies the requirements of ORS 459A.320.
(2) Not later than 60 days after receiving a plan under ORS 359A.320, the department shall either approve, approve with conditions or reject the plan. If the department rejects the plan, the department shall provide the reason or reasons for the rejection. An electronics producer responsibility organization must submit a revised plan to the department no later than 45 days after the date of the rejection.
(3) No later than 45 days after receiving a revised plan under subsection (2) of this section, the department shall either approve, approve with conditions or reject the revised plan.
(4) If the department rejects a revised plan, the department may:
(a) Require the electronics producer responsibility organization to further revise the plan in accordance with a timeline set forth by the department;
(b) Direct changes to the revised plan; or
(c) Direct the manufacturer or manufacturers on whose behalf the revised plan was submitted to register with an electronics producer responsibility organization with an approved plan.
(5) If the department directs changes to a revised plan under subsection (4) of this section, the electronics producer responsibility organization must implement the changes or request a hearing under ORS chapter 183.