3031.205-32 Precontract costs.
United States · 48 CFR — Federal Acquisition Regulations System · Status: effective
Cite this
- Citation
- 48 CFR 3031.205-32, 3031.205-32 Precontract costs, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/253139
- Permanent ID
ys:prov:253139@1- SHA-256
04d96e47ffb4c8a32428f66851f861a99e90080c7ad6f24942dd144c7610dfd1
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) The decision to incur precontract costs is that of the contractor. DHS employees may not authorize, demand, or require a contractor to incur precontract costs. The contracting officer must advise the prospective contractor that any costs incurred before contract award are incurred at the contractor's sole risk and that if negotiations fail to result in a binding contract, payment of these costs will not be made by the Government. See (HSAR) 48 CFR 3031.205-32(b) regarding exception due to reconciliation of costs.
(b) When the contracting officer determines that incurring precontract costs was necessary to meet the proposed contract delivery schedule of a cost-reimbursement contract, the clause at (HSAR) 48 CFR 3052.231-70, Precontract Costs, may be inserted in the resultant contract.