48 CFR 3052.216-72
3052.216-72 Performance evaluation plan.
United States · 48 CFR — Federal Acquisition Regulations System · Status: effective
Cite this
- Citation
- 48 CFR 3052.216-72, 3052.216-72 Performance evaluation plan, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/253241
- Permanent ID
ys:prov:253241@1- SHA-256
be46dece87f3173741248a42e8436d5fd0eabd2337d681e5ebcc82fd4dcdfc7d
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
As prescribed in (HSAR) 48 CFR 3016.406(e)(i)(ii), insert a clause substantially the same as the following:
(a) A Performance Evaluation Plan shall be unilaterally established by the Government based on the criteria stated in the contract and used for the determination of award fee. This plan shall include the criteria used to evaluate each area and the percentage of award fee (if any) available for each area. A copy of the plan shall be provided to the contractor ___ (insert number) calendar days prior to the start of the first evaluation period.
(b) The criteria contained within the Performance Evaluation Plan may relate to:
(1) Technical (including schedule) requirements if appropriate;
(2) Management; and (3) Cost.
(c) The Performance Evaluation Plan may, consistent with the contract, be revised unilaterally by the Government at any time during the period of performance. Notification of such changes shall be provided to the contractor ___ (insert number) calendar days prior to the start of the evaluation period to which the change will apply.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.