yourstate.us
48 CFR 3052.217-94

3052.217-94 Lay days (USCG).

United States · 48 CFR — Federal Acquisition Regulations System · Status: effective

Get this as JSONEmbed this
Cite this
Citation
48 CFR 3052.217-94, 3052.217-94 Lay days (USCG), United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/253248
Permanent ID
ys:prov:253248@1
SHA-256
7a3d683171f2b71f1e1fce30dcab9ae04db386f039e4b035eed381fc9e7bb9b2

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

As prescribed in USCG guidance at (HSAR) 48 CFR 3017.9000(a) and (b), insert the following clause: (a) Lay day time will be paid by the Government at the Contractor's stipulated bid price for this item of the contract when the vessel remains on the dry dock or marine railway as a result of any change that involves work in addition to that required under the basic contract. (b) No lay day time shall be paid until all items of the basic contract for which a price was established by the Contractor and for which docking of the vessel was required have been satisfactorily completed and accepted. (c) Days of hauling out and floating, whatever the hour, shall not be paid as lay day time, and days when no work is performed by the Contractor shall not be paid as lay day time. (d) Payment of lay day time shall constitute complete compensation for all costs, direct and indirect, to reimburse the Contractor for use of dry dock or marine railway.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.