49 CFR 24.306
§ 24.306 Discretionary utility relocation payments.
United States · 49 CFR — Transportation · Status: effective
Cite this
- Citation
- 49 CFR 24.306, § 24.306 Discretionary utility relocation payments, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/254458
- Permanent ID
ys:prov:254458@1- SHA-256
73306e31794ab377fb78b18031ad9960a54f75f4949d54532816094062ba7b4c
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) Whenever a program or project undertaken by an agency causes the relocation of a utility facility (defined at § 24.2(a)) and the relocation of the facility creates extraordinary expenses for its owner, the agency may, at its option, make a relocation payment to the owner for all or part of such expenses, if the following criteria are met:
(1) The utility facility legally occupies State or local government property, or property over which the State or local government has an easement or right-of-way;
(2) The utility facility's right of occupancy thereon is pursuant to State law or local ordinance specifically authorizing such use, or where such use and occupancy has been granted through a franchise, use and occupancy permit, or other similar agreement;
(3) Relocation of the utility facility is required by and is incidental to the primary purpose of the project or program undertaken by the agency;
(4) There is no Federal law, other than the Uniform Act, which clearly establishes a requirement for the payment of utility moving costs that is applicable to the agency's program or project; and
(5) State or local government reimbursement for utility moving costs or payment of such costs by the agency is in accordance with State law.
(b) For the purposes of this section, the term extraordinary expenses mean those expenses which, in the opinion of the agency, are not routine or predictable expenses relating to the utility's occupancy of rights-of-way, and are not ordinarily budgeted as operating expenses, unless the owner of the utility facility has explicitly and knowingly agreed to bear such expenses as a condition for use of the property or has voluntarily agreed to be responsible for such expenses.
(c) A relocation payment to a utility facility owner for moving costs under this section may not exceed the cost to functionally restore the service disrupted by the federally assisted program or project, less any increase in value of the new facility and salvage value of the old facility. The agency and the utility facility owner shall reach prior agreement on the nature of the utility relocation work to be accomplished, the eligibility of the work for reimbursement, the responsibilities for financing and accomplishing the work, and the method of accumulating costs and making payment. (See appendix A to this part, section 24.306.)
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.