49 CFR 192.329

§ 192.329 Installation of plastic pipelines by trenchless excavation.

United States · 49 CFR — Transportation · Status: effective

Get this as JSONEmbed this
Cite this
Citation
49 CFR 192.329, § 192.329 Installation of plastic pipelines by trenchless excavation, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/257126
Permanent ID
ys:prov:257126@1
SHA-256
1d834846632f864decb7326736d161af227fe054614b3aeee218a83bcc9a2087

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

Plastic pipelines installed by trenchless excavation must comply with the following: (a) Each operator must take practicable steps to provide sufficient clearance for installation and maintenance activities from other underground utilities and/or structures at the time of installation. (b) For each pipeline section, plastic pipe and components that are pulled through the ground must use a weak link, as defined by § 192.3, to ensure the pipeline will not be damaged by any excessive forces during the pulling process.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.