49 CFR 192.452
§ 192.452 How does this subpart apply to converted pipelines and regulated onshore gathering pipelines?
United States · 49 CFR — Transportation · Status: effective
Cite this
- Citation
- 49 CFR 192.452, § 192.452 How does this subpart apply to converted pipelines and regulated onshore gathering pipelines?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/257149
- Permanent ID
ys:prov:257149@1- SHA-256
bdb8dd9630f8cc333d037450df2fad2c079f717cacc10c6f5aac6e19ed6c395a
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) Converted pipelines. Notwithstanding the date the pipeline was installed or any earlier deadlines for compliance, each pipeline which qualifies for use under this part in accordance with § 192.14 must meet the requirements of this subpart specifically applicable to pipelines installed before August 1, 1971, and all other applicable requirements within 1 year after the pipeline is readied for service. However, the requirements of this subpart specifically applicable to pipelines installed after July 31, 1971, apply if the pipeline substantially meets those requirements before it is readied for service or it is a segment which is replaced, relocated, or substantially altered.
(b) Type A and B onshore gathering lines. For any Type A or Type B regulated onshore gathering line under § 192.9 existing on April 14, 2006, that was not previously subject to this part, and for any onshore gathering line that becomes a regulated onshore gathering line under § 192.9 after April 14, 2006, because of a change in class location or increase in dwelling density:
(1) The requirements of this subpart specifically applicable to pipelines installed before August 1, 1971, apply to the gathering line regardless of the date the pipeline was actually installed; and
(2) The requirements of this subpart specifically applicable to pipelines installed after July 31, 1971, apply only if the pipeline substantially meets those requirements.
(c) Type C onshore regulated gathering lines. For any Type C onshore regulated gathering pipeline under § 192.9 existing on May 16, 2022, that was not previously subject to this part, and for any Type C onshore gas gathering pipeline that becomes subject to this subpart after May 16, 2022, because of an increase in MAOP, change in class location, or presence of a building intended for human occupancy or other impacted site:
(1) The requirements of this subpart specifically applicable to pipelines installed before August 1, 1971, apply to the gathering line regardless of the date the pipeline was actually installed; and
(2) The requirements of this subpart specifically applicable to pipelines installed after July 31, 1971, apply only if the pipeline substantially meets those requirements.
(d) Regulated onshore gathering lines generally. Any gathering line that is subject to this subpart per § 192.9 at the time of construction must meet the requirements of this subpart applicable to pipelines installed after July 31, 1971.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.