49 CFR 192.749
§ 192.749 Vault maintenance.
United States · 49 CFR — Transportation · Status: effective
Cite this
- Citation
- 49 CFR 192.749, § 192.749 Vault maintenance, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/257246
- Permanent ID
ys:prov:257246@1- SHA-256
51278ce04fb89f654498b40ce4521b70b820605dac3b8c57cfe09db1db24c6ee
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) Each vault housing pressure regulating and pressure limiting equipment, and having a volumetric internal content of 200 cubic feet (5.66 cubic meters) or more, must be inspected at intervals not exceeding 15 months, but at least once each calendar year, to determine that it is in good physical condition and adequately ventilated.
(b) If gas is found in the vault, the equipment in the vault must be inspected for leaks, and any leaks found must be repaired.
(c) The ventilating equipment must also be inspected to determine that it is functioning properly.
(d) Each vault cover must be inspected to assure that it does not present a hazard to public safety.
Legislative history