yourstate.us
49 CFR 192.931

§ 192.931 How may Confirmatory Direct Assessment (CDA) be used?

United States · 49 CFR — Transportation · Status: effective

Get this as JSONEmbed this
Cite this
Citation
49 CFR 192.931, § 192.931 How may Confirmatory Direct Assessment (CDA) be used?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/257274
Permanent ID
ys:prov:257274@1
SHA-256
cfcc281aba4127d43ff9ce512d7fb0bb3419a9322374af84e05b6e7d823a0ce0

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

An operator using the confirmatory direct assessment (CDA) method as allowed in § 192.937 must have a plan that meets the requirements of this section and of §§ 192.925 (ECDA) and § 192.927 (ICDA). (a) Threats. An operator may only use CDA on a covered segment to identify damage resulting from external corrosion or internal corrosion. (b) External corrosion plan. An operator's CDA plan for identifying external corrosion must comply with § 192.925 with the following exceptions. (1) The procedures for indirect examination may allow use of only one indirect examination tool suitable for the application. (2) The procedures for direct examination and remediation must provide that— (i) All immediate action indications must be excavated for each ECDA region; and (ii) At least one high risk indication that meets the criteria of scheduled action must be excavated in each ECDA region. (c) Internal corrosion plan. An operator's CDA plan for identifying internal corrosion must comply with § 192.927 except that the plan's procedures for identifying locations for excavation may require excavation of only one high risk location in each ICDA region. (d) Defects requiring near-term remediation. If an assessment carried out under paragraph (b) or (c) of this section reveals any defect requiring remediation prior to the next scheduled assessment, the operator must schedule the next assessment in accordance with NACE SP0502 (incorporated by reference, see § 192.7), section 6.2 and 6.3. If the defect requires immediate remediation, then the operator must reduce pressure consistent with § 192.933 until the operator has completed reassessment using one of the assessment techniques allowed in § 192.937.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.