yourstate.us
49 CFR 195.304

§ 195.304 Test pressure.

United States · 49 CFR — Transportation · Status: effective

Get this as JSONEmbed this
Cite this
Citation
49 CFR 195.304, § 195.304 Test pressure, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/257515
Permanent ID
ys:prov:257515@1
SHA-256
5e5f7a593e5d02af63c766b5aab01faee487c1c3b1a5076e69e37786edd98376

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

The test pressure for each pressure test conducted under this subpart must be maintained throughout the part of the system being tested for at least 4 continuous hours at a pressure equal to 125 percent, or more, of the maximum operating pressure and, in the case of a pipeline that is not visually inspected for leakage during the test, for at least an additional 4 continuous hours at a pressure equal to 110 percent, or more, of the maximum operating pressure.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.