49 CFR 195.406
§ 195.406 Maximum operating pressure.
United States · 49 CFR — Transportation · Status: effective
Cite this
- Citation
- 49 CFR 195.406, § 195.406 Maximum operating pressure, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/257528
- Permanent ID
ys:prov:257528@1- SHA-256
91cae36c9408dd95923198f162c80267d57866e894b0b8338c41c3fdd1bfccd3
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) Except for surge pressures and other variations from normal operations, no operator may operate a pipeline at a pressure that exceeds any of the following:
(1) The internal design pressure of the pipe determined in accordance with § 195.106. However, for steel pipe in pipelines being converted under § 195.5, if one or more factors of the design formula (§ 195.106) are unknown, one of the following pressures is to be used as design pressure:
(i) Eighty percent of the first test pressure that produces yield under section N5.0 of appendix N of ASME B31.8 (incorporated by reference, see § 195.3), reduced by the appropriate factors in §§ 195.106 (a) and (e); or
(ii) If the pipe is 12 3/4 inch (324 mm) or less outside diameter and is not tested to yield under this paragraph, 200 p.s.i. (1379 kPa) gage.
(2) The design pressure of any other component of the pipeline.
(3) Eighty percent of the test pressure for any part of the pipeline which has been pressure tested under subpart E of this part.
(4) Eighty percent of the factory test pressure or of the prototype test pressure for any individually installed component which is excepted from testing under § 195.305.
(5) For pipelines under §§ 195.302(b)(1) and (b)(2)(i) that have not been pressure tested under subpart E of this part, 80 percent of the test pressure or highest operating pressure to which the pipeline was subjected for 4 or more continuous hours that can be demonstrated by recording charts or logs made at the time the test or operations were conducted.
(b) No operator may permit the pressure in a pipeline during surges or other variations from normal operations to exceed 110 percent of the operating pressure limit established under paragraph (a) of this section. Each operator must provide adequate controls and protective equipment to control the pressure within this limit.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.