§ 195.413 Underwater inspection and reburial of pipelines in the Gulf of America and its inlets.
United States · 49 CFR — Transportation · Status: effective
Cite this
- Citation
- 49 CFR 195.413, § 195.413 Underwater inspection and reburial of pipelines in the Gulf of America and its inlets, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/257532
- Permanent ID
ys:prov:257532@1- SHA-256
83050524fb2efa15a04fe7b04686285e46e4b0eb71169b61ea701937e5c4ec8e
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) Except for gathering lines of 4 1/2 inches (114mm) nominal outside diameter or smaller, each operator shall prepare and follow a procedure to identify its pipelines in the Gulf of America and its inlets in waters less than 15 feet (4.6 meters) deep as measured from mean low water that are at risk of being an exposed underwater pipeline or a hazard to navigation. The procedures must be in effect August 10, 2005.
(b) Each operator shall conduct appropriate periodic underwater inspections of its pipelines in the Gulf of America and its inlets in waters less than 15 feet (4.6 meters) deep as measured from mean low water based on the identified risk.
(c) If an operator discovers that its pipeline is an exposed underwater pipeline or poses a hazard to navigation, the operator shall—
(1) Promptly, but not later than 24 hours after discovery, notify the National Response Center, telephone: 1-800-424-8802, of the location and, if available, the geographic coordinates of that pipeline.
(2) Promptly, but not later than 7 days after discovery, mark the location of the pipeline in accordance with 33 CFR Part 64 at the ends of the pipeline segment and at intervals of not over 500 yards (457 meters) long, except that a pipeline segment less than 200 yards (183 meters) long need only be marked at the center; and
(3) Within 6 months after discovery, or not later than November 1 of the following year if the 6 month period is later than November 1 of the year of discovery, bury the pipeline so that the top of the pipe is 36 inches (914 millimeters) below the underwater natural bottom (as determined by recognized and generally accepted practices) for normal excavation or 18 inches (457 millimeters) for rock excavation.
(i) An operator may employ engineered alternatives to burial that meet or exceed the level of protection provided by burial.
(ii) If an operator cannot obtain required state or Federal permits in time to comply with this section, it must notify OPS; specify whether the required permit is State or Federal; and, justify the delay.