§ 230.50 Time of testing.

United States · 49 CFR — Transportation · Status: effective

Get this as JSONEmbed this
Cite this
Citation
49 CFR 230.50, § 230.50 Time of testing, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/258661
Permanent ID
ys:prov:258661@1
SHA-256
9952ce14e09f44471edfdd2508957b47553b5a76958fc3878105c3df91367b9d

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

All safety relief valves shall be tested, and adjusted if necessary, under steam at every 92 service day inspection, and also whenever any irregularity is reported.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.