49 CFR 230.61
§ 230.61 Arch tubes, water bar tubes, circulators and thermic siphons.
United States · 49 CFR — Transportation · Status: effective
Cite this
- Citation
- 49 CFR 230.61, § 230.61 Arch tubes, water bar tubes, circulators and thermic siphons, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/258672
- Permanent ID
ys:prov:258672@1- SHA-256
7f8d3cdf6a4fd01d5cea502dcdcd8f1e4c0dbe35c2c4fe4acfe0f8636863c7b9
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) Frequency of cleaning. Each time the boiler is washed, arch tubes and water bar tubes shall thoroughly be cleaned mechanically, washed, and inspected. Circulators and thermic siphons shall thoroughly be cleaned, washed and inspected.
(b) Defects. Arch tubes and water bar tubes found blistered, bulged, or otherwise defective shall be renewed. Circulators and thermic siphons found blistered, bulged or otherwise defective shall be either repaired or renewed.
(c) Method of examination. Arch tubes, water bar tubes and circulators shall be examined using an appropriate NDE method that accurately measures wall thickness at each annual inspection. All arch brick shall be removed for this inspection. If any are found with wall thickness reduced below that required to render them safe and suitable for the service intended at the MAWP specified on the boiler specification FRA Form No. 4, they must be replaced or repaired. (See appendix B of this part.)
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.