49 CFR 260.19
§ 260.19 Preapplication meeting.
United States · 49 CFR — Transportation · Status: effective
Cite this
- Citation
- 49 CFR 260.19, § 260.19 Preapplication meeting, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/259773
- Permanent ID
ys:prov:259773@1- SHA-256
40f2c08f33a2c52fc4cb8e96aaa48972c1836248da356016f5941f7089fe071b
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
Potential Applicants may request a meeting with the FRA Associate Administrator for Railroad Development to discuss the nature of the project being considered. Applicants must be prepared to provide at least the following information:
(a) Applicant's name, address, and contact person;
(b) Name of the proposed infrastructure partner(s), if any, including the identification of potential amounts of funding from each;
(c) Amount of the direct loan or loan guarantee request, and a description of the technical aspects of the project including a map of the existing railroad lines with the location of the project indicated;
(d) Brief description and estimate of the economic impact, including future demand for service, improvements that can be achieved, the project's relation to the priorities listed in § 260.7, along with any feasibility, market or other studies that may have been done as attachments;
(e) Amount of Applicant's equity and a description of collateral offered, with estimated values, including the basis of such, to be offered as security for the loan;
(f) If applicable, the names and addresses of the Applicant's parent, affiliates, and subsidiary corporations, if any, and a description of the ownership relationship and the level of guarantee, if any, to be offered;
(g) For existing companies, a current balance sheet and an income statement not more than 90 days old and financial statements for the borrower and any parent, affiliates, and subsidiaries for at least the four most recent years; and
(h) Information relevant to the potential environmental impacts of the project in the context of applicable Federal law.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.