Kan. Stat. Ann. § 75-5676
Deadline for issuance of permits to discharge stormwater runoff from construction activities under the national pollutant discharge elimination system general permit or rainfall erosivity waivers; complete application required; section not to supersede federal law
Kansas · Kansas Statutes Annotated Chapter 75 — State Departments; Public Officers and Employees · Status: effective
Cite this
- Citation
- Kan. Stat. Ann. § 75-5676, Deadline for issuance of permits to discharge stormwater runoff from construction activities under the national pollutant discharge elimination system general permit or rainfall erosivity waivers; complete application required; section not to supersede federal law, Kansas, version 1 as recorded 2026-10-04, yourstate.us, https://yourstate.us/provision/2608549
- Permanent ID
ys:prov:2608549@1- SHA-256
0796fdee9d88227e5b4d6344e36d2a9f1cca2727c88cb719fbca9b22b2996fed
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
Within 45 days of the submittal by an applicant to the department of health and environment of a complete notice of intent to discharge stormwater runoff from construction activities requesting authorization to discharge stormwater runoff from construction activities under the federal national pollutant discharge elimination system general permit or a rainfall erosivity waiver application and including all supporting documentation pursuant to applicable federal or state law, the secretary of health and environment shall issue an authorization, waiver or denial, as determined by the secretary, to the applicant. The provisions of this section shall not be construed to supersede conflicting federal law.